by ChapTin | Aug 27, 2018 | Malone Bridge
Summary of Work Completed Last Month Week of July 30th – Finished pilings, began substructure concrete forms and reinforcement. Week of August 6th – Continued substructure concrete forms and reinforcement, poured substructure concrete. Week of August 13th...