Malone Bridge Project Update – 10/11/2018

This Week: Gravels down.  KLC will be slipping the curb Saturday if all goes well – everything hinges on them now, but not verified yet. Next Week: Utilities: Cable TV moves back behind curb. ECE may schedule to bury electric wires and set lights end of week....

Project Update – August 27, 2018

Summary of Work Completed Last Month Week of July 30th – Finished pilings, began substructure concrete forms and reinforcement. Week of August 6th – Continued substructure concrete forms and reinforcement, poured substructure concrete. Week of August 13th...

Project Update – June 6, 2018

Summary of Scheduled Work June 11th – Finishing west forcemain tie in, test watermain June 12th – Test watermain, begin storm sewer June 13th – Centerpoint Energy gas main relocation, remove temporary water service, continue storm sewer June 14th...