Summary of Work Completed Last Month

  • Week of July 30th – Finished pilings, began substructure concrete forms and reinforcement.
  • Week of August 6th – Continued substructure concrete forms and reinforcement, poured substructure concrete.
  • Week of August 13th – Stripped substructure formwork, backfilled abutments, placed rip rap and began deck false work.
  • Week of August 20th – Continued deck false work/formwork and placed rip rap.

Summary of Work Scheduled Next Month

  • Week of August 27th – Deck reinforcement and concrete deck pour (pour scheduled for Friday)
  • Week of September 3rd – Strip deck formwork and falsework
  • Week of September 16th – Bridge railing and paint.  Switch traffic to new bridge.  Removal temporary bridge.

The project is currently on schedule