Summary of Work Completed Last Month
- Week of July 30th – Finished pilings, began substructure concrete forms and reinforcement.
- Week of August 6th – Continued substructure concrete forms and reinforcement, poured substructure concrete.
- Week of August 13th – Stripped substructure formwork, backfilled abutments, placed rip rap and began deck false work.
- Week of August 20th – Continued deck false work/formwork and placed rip rap.
Summary of Work Scheduled Next Month
- Week of August 27th – Deck reinforcement and concrete deck pour (pour scheduled for Friday)
- Week of September 3rd – Strip deck formwork and falsework
- Week of September 16th – Bridge railing and paint. Switch traffic to new bridge. Removal temporary bridge.
The project is currently on schedule