Summary of Scheduled Work
- June 11th – Finishing west forcemain tie in, test watermain
- June 12th – Test watermain, begin storm sewer
- June 13th – Centerpoint Energy gas main relocation, remove temporary water service, continue storm sewer
- June 14th – Continue storm sewer, prepare for traffic bypass work
- June 15th – Finish storm sewer, prepare for traffic bypass work
Project is currently on schedule.